Contruction progress
CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS – OCTOBER, 2017
Key project milestones:
- Commencement: July 2015
- Topping-out: April 2017
- Hand-over plan:
- Tower 3: Second Quarter of 2018
- Tower 4: Third Quarter of 2018
- Current status:
- Infrastructural work: 100% completed
- Apartment fit-out package: 80% completed
- Mechanical, Electrical, Piping, and Firefighting system: 90% completed
- Lift installation and Testing & commissioning: 95% completed
- Landscape:
- Hardscape’s structure: Completed. Especially 50m Swimming pool and planters
- Soft scape and finishing works started in August 2017
Promenade Tower
Crescent Tower
Swimming Pool
Landscape
Other News
Contruction progress
CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: TOPPING OUT CEREMONY OF PROMENADE & CRESCENT TOWERS – APRIL, 2017
Other News
Contruction progress
CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS – OCTOBER, 2016
October, 2016, the tower construction has already reached level 18 for both The Promenade and The Crescent.
Other News
Contruction progress
CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS
City Garden, a gated-community inspired by terraced rice fields in the Northwest of Vietnam, comprises six elliptical towers ranging from 21 to 30 floors and more than 900 residences. City Garden has a variety of layouts such as The Soho - 1 bedroom (69-72m2), The Cosmopolitan - 2 bedrooms (102-117 m2), The Metropolitan - 3 bedrooms (140-145 m2), and Penthouses (256-355 m2). In Phase 2 (currently under development). (...)