CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS – OCTOBER, 2017

  1. Key project milestones:

    • Commencement: July 2015
    • Topping-out: April 2017
    • Hand-over plan:
      • Tower 3: Second Quarter of 2018
      • Tower 4: Third Quarter of 2018
  2. Current status:
    • Infrastructural work: 100% completed
    • Apartment fit-out package: 80% completed
    • Mechanical, Electrical, Piping, and Firefighting system: 90% completed
    • Lift installation and Testing & commissioning: 95% completed
    • Landscape:
      • Hardscape’s structure: Completed. Especially 50m Swimming pool and planters
      • Soft scape and finishing works started in August 2017

Promenade Tower

Crescent Tower

Swimming Pool

Landscape

Other News

建造进度

CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS – OCTOBER, 2016

October, 2016, the tower construction has already reached level 18 for both The Promenade and The Crescent.

Other News

建造进度

CONSTRUCTION PROGRESS UPDATE FOR PHASE 2: PROMENADE AND CRESCENT TOWERS

City Garden, a gated-community inspired by terraced rice fields in the Northwest of Vietnam, comprises six elliptical towers ranging from 21 to 30 floors and more than 900 residences. City Garden has a variety of layouts such as The Soho - 1 bedroom (69-72m2), The Cosmopolitan - 2 bedrooms (102-117 m2), The Metropolitan - 3 bedrooms (140-145 m2), and Penthouses (256-355 m2). In Phase 2 (currently under development). (...)